Case studies

Man Group plc
Reducing the risk for Man Group through project monitoring Appraised the design and monitored the construction of Riverbank House- Location London
- Key figures 320,000 sq ft New Build
- Additional Information Chris Tucker +44(0) 20 7338 4016
The results
- Enhanced specification for future flexibility
- Identified potential defects / high maintenance risks requiring developer to remedy and ensuring a higher quality is achieved
- Reduced long term maintenance and dilapidations costs
- Additional tenants plant space
- Major changes included as tenants modifications to improve resilience and minimise base building changes during fitting out with significant cost and time benefits
- Enhanced performance in terms sustainability and operation.
The challenges
- Defining the space, brief and occupational requirements five years before occupation in particular potential tenants’ modifications before the interior design had been developed.
What we did
- Negotiated an enhanced base build specification and provided construction input on the various legal agreements
- Introduced significant tenants modifications to meet the occupational requirements in particular enhanced resilience
- Appraised and approved designs as they progressed
- Monitored construction to ensure compliance with specifications and standards, enhanced quality and improved operational performance.